Letters Home

1st October 2017

Pedestrian Improvements Around Kingston Avenue Site

Further to a consultation in August of local residents about proposed improvements for pedestrians around our Kingston site, officers and councillors at Sutton Council have considered all the responses and decided that the improvements should be implemented.

The scheme will include installing coloured pencil bollards, new school flashing signs and will tighten the radius of some junctions as shown on the scheme plan. The bollards and the kerb works at the junctions will not prevent access to existing driveways.

This work has been programmed to start on 2 November 2016. The contractor undertaking the work is R J Dance Contractors and the works will take approximately three weeks to complete. The council will be working with the contractor to ensure the work is completed as quickly and safely as possible.

If you have any concerns regarding this work please contact Rud Francois by way of Sutton Council’s contact centre on 020 8770 6455 or email traffic.postbook@sutton.gov.uk.